Sample Maintenance Audit
Widget (International) Ltd
Report
Presentation
(Click
on a subject heading for navigation)
Section
1. Site
Operations
Section2.
Maintenance Organisation
Section
3. Operational
Management Perceptions
Section
4. Maintenance
Policy and Strategy
Section
5. Maintenance
Planning and Control Systems
Section
6. Compliance
With Safety Regulations
Section
7. Preventive
Maintenance Activity
Section
8. Performance
Management
Section
9.
"People" Systems
Section
10. Contractor Control
Section
11. Stores Systems
Section
12. Best Practice
Benchmarks
Section
13. Observations and
Conclusions
Section
14. Opportunities for
Improvement
This report covers the results of an audit of
the maintenance function at Widget (International) Ltd by Frank Chambers of
PRIME on 12th December 2002. It is intended that the report will provide Widget
with an insight of their maintenance operations such that it can be used to
support a viable performance improvement programme.
1. Widget’s
Operations
Widget is a US-owned manufacturer of
engineering parts, and the largest manufacturer of fasteners for complex systems
in Europe. The Birtley plant manufactures custom-designed parts in a wide range
of sizes and arrangements, principally for use in the chemicals, process and
aeronautical industries. The Birtley facility operates on a 3-shift, 5-day basis
covering a 120-hour working
week.
{Top of Page]
2. Widget’s
Maintenance Organisation
The Widget internal engineering team is
managed by the Production Engineer who reports through the production line
management system to the Operations Manager (the Production Engineer spends less
than 50% of his time on maintenance management activity). There are a total of 9
craftsmen covering the production shifts as below :
|
|
Mechanical |
Electrical |
|
Early Shift |
3 |
1 |
|
Late Shift |
2 |
1 |
|
Night Shift |
1 |
1 |
Contractors are used to carry out servicing on
site utilities and building infrastructure, coded welding support and for
providing cover for craftsmen when
required.
{Top of Page]
3. Senior
Management Perceptions of Maintenance
The improvement priority for the Maintenance
Department is to improve the operational availability of the manufacturing
process lines in order to strategically position Widget to be able to take up
additional production activity without capital expenditure, or to reduce
operational hours of selected production cells. Additionally, any possible
improvement in the direct cost of maintenance, and in the impact of maintenance
on product quality, would be welcomed.
Production management perceive the current
maintenance operation to be reactive in nature, with less than satisfactory
levels of preventive maintenance, and with a low level of effort directed to
downtime reduction. The level of craft skills, application of engineering
standards and the response to breakdowns is considered to be good, as is the
level of safe working of the craft team. Management of engineering spares is
perceived to be poor.
The maintenance department is perceived
to be insufficiently integrated into the manufacturing operation. Overall, the
‘Value-for-Money’ rating of the delivered maintenance service is considered
to be average. {Top of Page]
4. Widget’s
Maintenance Policy and Strategies
There is no written policy for the maintenance
department. The maintenance strategies that are in place comprise a major
service on key machines, and on statutory requirements.
Maintenance is not fully integrated into
manufacturing management operations. A formal Kaisen system is in place for
generating continuous improvement in manufacturing, including maintenance
operations where appropriate. The differentiated maintenance roles and
responsibilities for the Production Manager and the Production Engineer are not
clear.
The effectiveness of the maintenance operation
has not been benchmarked against other similar companies, either within the
Widget group of companies or in a wider
context.
{Top of Page]
5. Widget’s
Maintenance Planning and Control Systems.
The system for requesting maintenance services
is by raising a maintenance work request form although this is often not
followed, leading to a predominance of verbally requested work.
The only work which receives any forethought
and planning is for the preventive maintenance work. All of the remaining (85%)
of maintenance activity is of an emergency breakdown nature, precipitated by
equipment failures that halt the production process.
50% of plant is subject to some form of
preventive activity, this being solely for a major service on key equipment,
which has been in place for about 18 months.
No records are retained in any formal way for
maintenance history purposes although it is possible that some information could
be retrieved laboriously from paper records.
There is no form of CMMS (Computerised
Maintenance Management System) in place, although an evaluation of the Shire
"Frontline" system is currently being carried out.
Maintenance work procedures tend to be
unwritten, relying on an individual craftsman’s experience. Although
up-to-date manuals exist for most equipment they tend not to be used by
craftsmen.
There is a clear identification system for all
equipment, used by both production and maintenance personnel, with commonly used
and understood I/D numbers. {Top of Page]
6. Compliance
with Safety Regulations
The occurrence of LTAs in the maintenance
workforce is very low, with no accidents reported in the past several years
(Best Practice levels would be around 1 LTA in more than 0.5 million man-hours).
Minor accident levels are also fairly low, with a level of about 1 minor
accident in 7000 man-hours. Compliance with the most applicable legislation
suggests a generally satisfactory level of compliance although there are a
number of areas where compliance appears to warrant more detailed auditing,
namely :
· The absence of
recording of maintenance work (this is an implied requirement under H&SAW
Act and PUWER Regs).
· Compliance
with the requirements of ACOP L8 for Legionella appears to be incomplete, in
that there appears to be a lack of detailed layouts and risk assessments for
hot/cold water distribution systems, and no regular monitoring of hot water
temperature profiles.
· There is no
copy of the Written Scheme for Examinations of Pressure Systems available on
site, and the Insurance Company responsible for inspections is not always
informed when modifications are made to the system.
· There is no
formal lockoff/tagging system for electrical isolations although the standard
practice is to isolate and remove fuses. However, as the electrical
distribution boards are not secured, this would not be seen to be adequate.
· There appears
to be a lack of regular, formal testing of machine guards, required under
PUWER
Regulations.
{Top of Page]
7. Preventive
Maintenance Activity
PPM programmes are applied to approximately
60% of the production equipment. The PPM routines, which were introduced in the
past six months, are based around single major service inspections developed
from maker’s recommendations. The major service inspections, which are
scheduled on a calendar basis (ie they reflect theoretical, not actual, runhours),
are totally intrusive and typically incur about 50 hours of equipment downtime
to carry out. If the equipment is fully occupied, this will involve a downtime
level of about 2.5%; if the equipment is only operational on 2 shifts, the
overall downtime level will be 4%. No form of formal FMECA (Failure Mode, Effect
and Criticality Assessment) has been used to assess the effectiveness and
appropriateness of the PM programme.
A programme of equipment lubrication is
included in the major service inspections and there are no interim lubrication
schedules.
There is no application of CBM
(Condition-Based Maintenance) or routine running equipment inspection, either
‘3-Sense Testing’ or supported by inspection tools.
No routine checks are carried out on equipment
alarms and trips systems.
The PPM tasks are currently scheduled using a
paper-based system although it is planned to move to computer-based scheduling
in the future, which will also provide for scheduling by runhours as an
alternative to calendar scheduling.
8. Performance
Management
There are essentially no measures for
maintenance performance in terms of its impact on production. Equipment downtime
is included in the operator’s shift reports, but the data is not used for
routine reporting and is not communicated to the maintenance team.
Because downtime information is not available
to the Plant Engineer, there is no formal system for downtime reduction based on
Root Cause Elimination.
The use of OEE (Overall Equipment
Effectiveness) as a tool for measurement of all throughput losses has been
evaluated in the past although no scheme for formalising OEE measurement across
the plant has been considered.
There is no system for budgeting maintenance
activity, or for reporting maintenance cost in a way that would support a cost
reduction programme. However, year-on-year cost reductions have been achieved in
the maintenance area.
No annual management objectives are set in the
maintenance
area.
{Top of Page]
9. "People"
Systems
Craftsmen have a relatively high level of
empowerment to carry out work unsupervised. However, there is little
cross-skilling between mechanical and electrical crafts, partly as a result of
the traditional demarcation lines drawn by the craft unions to which all the
craftsmen belong. Engineering staff carry out almost all maintenance work -
production operators are involved in virtually no maintenance-related
activities, and in fact are not even effective in regular machine cleaning.
Relationships between management and the
maintenance workforce are good, although it is difficult to introduce effective
change due to the entrenched Trade Union culture.
Overtime levels are high, at 15% of worked
hours.
The training level is less than 1.5% of the
maintenance budget. {Top of
Page]
10. Contractor
Controls
There is no system of contractor evaluation
prior to selection, or of regular auditing of performance. Simple ‘Rules for
Contractors’ are in place and are applied whenever a contractor presents
himself at the plant, but are often not enforced. Contract companies can supply
any craftsmen, with no controls in place for confirming their individual
competence.
No partnership or single-supplier arrangements
have been investigated. Service contracts are renegotiated formally when they
are due for renewal. {Top
of Page]
11. Stores
Systems
The engineering store is unmanned, with free
access to all. The stock, which is not insubstantial, is unmanaged in that there
are no records of inventory quantity or value, and no recording of issues and
receipts. It was reported that a considerable amount of craftsman time is lost
searching for
materials.
{Top of Page]
12. ‘Best
Practice’ Benchmarks
Because of the difficulty in making precise
comparisons between differing manufacturing operations it is not advisable to
draw distinct conclusions on the basis of maintenance ‘Best Practice’
metrics comparisons alone, nor should they be viewed as being entirely
indicative of the situation at Widget in view of the relatively small scale of
the maintenance operation. However, they do provide insights into the areas
available for improvement and can indicate the potential scale of any
improvement opportunities.
The metrics which have been compiled for
Widget’s operations based on the information provided to PRIME are presented
the separate Metrics Report and Profit Datasheet documents. General
conclusions that can be drawn from the comparisons of the key performance
indicators are:
· The results
indicate that the cost of maintenance at Widget as a proportion of all
manufacturing costs is higher than in the best companies. This adverse
comparison also applies to the ratio of maintenance cost to the replacement
value of the plant and equipment. The amount of replacement value and
maintenance cost borne by each craftsman is lower than Best Practice levels.
These comparisons would suggest that there are opportunities to improve both
the effectiveness of the maintenance operation and the internal efficiency
of the maintenance team, although there may well be organisational
constraints that will limit the degree to which cost reductions can be
achieved without affecting equipment support levels.
· There are no
precise measurements available for equipment downtime due to engineering
although anecdotal evidence based on sampling would indicate that downtime
is no lower than 8%. Over 2% downtime is incurred from the existing PPM
programme alone.
· The backlog
level is low. This usually leads to low efficiency in the craftsmen team
because of the inability to cope with low activity levels, although this is
probably not significant at Widget at present because of the relatively low
staffing levels. A low backlog level also tends to drive toward a reactive
maintenance culture in both maintenance and production, and this is true in
Widget. However, the lack of a system for managing work requests probably
works against jobs being raised at the earliest time, and the ‘real’
backlog may well be greater than 1 week. About 2 to 3 weeks of backlog would
be usual in an effective and well-regulated maintenance environment
· The
indicators showing ratios of direct employees to the numbers of indirects,
supervisors and planners are unlikely to be appropriate for comparison at
Widget due to the relatively small numbers of people involved.
· The
low level of expenditure on training is probably another element in the
relatively low effectiveness level.
· The
reasonable level of PPM coverage at 60% of all equipment is not consistent
with the high downtime levels and the high level of emergency breakdown
work. This suggests that, either the PPM programme is not optimised and has
not resulted in improvement in reliability, or that the craftsmen are
inactive at times when there are no breakdowns, or that both situations
apply.
{Top of Page]
13.
Observations and Conclusions
There are a number of important conclusions
that can be drawn from the audit.
· There are
two ways to minimise equipment downtime due to in-service failures, firstly
to improve plant reliability by eliminating repetitive failure causes, and
secondly to minimise the duration of repair intervention events. In the past
Widget have concentrated almost exclusively on the latter approach,
resulting a well-received repair culture. However, there are no long-term
reliability improvement programmes in place, and therefore continuous
management effort is required to maintain any gains in performance that have
been achieved by the fast response approach alone. There is a need to review
the strategies for maintenance to ensure that they are focussed on long
term, self-sustainable performance improvement that does not need to be
management-enforced.
· Although
there are measurement systems in place for downtime, this data is not
available to maintenance and is not structured to provide the information
they would need to support an improvement culture in maintenance. It has
been subjectively assessed that OEE levels, although not measured, are
probably less than 50% (this value is consistent with what would normally be
the starting position for companies which had not used historically used OEE
measurement). In this case it is likely that downtime resulting from
in-service failure of plant is likely to be no less than 8-10% (in line with
the anecdotal evidence indicating that it is no less than 8%).
· In
conjunction with the lack of engineering downtime data, the lack of
quantitative maintenance history from maintenance work records prevents the
practical application of an objective Root Cause Elimination programme.
· Based on
some assumptions made against the estimated OEE values, the total cost of
maintenance, including both direct and indirect costs, would appear to be in
the order of £1.3M (a cost escalation factor of 3.1 on direct cost against
Best Practice norms). This would certainly suggest that there is
considerable opportunity for performance improvement.
· The design
of the preventive maintenance routines are probably not optimised in that
they have not been based on any objective assessment of failure causes, have
essentially used maker’s recommended repair tasks, and have been developed
around intrusive maintenance techniques.
· A simplistic
cost/benefit assessment using the top level KPIs in the metrics report would
strongly suggest that significant performance improvement should be
achievable without any overall increase in maintenance cost. The KPIs would
also suggest that cost reduction should be possible, but this needs to be
assessed in the context of the lowest practical manning levels that would be
necessary to ensure satisfactory shift-by-shift coverage, and the special
skill sets required at Widget. {Top of Page]
14. Opportunities for
Improvement
As described in Section 13, the results from
the audit suggest that there are a number of opportunities to improve the
effectiveness of the maintenance service in Widget. The main recommendations
arising from the audit are as follows:
· Establish a
simple, clear policy/strategy for the maintenance function, agreed by all of
its ‘customers’, and based upon the current business drivers. (The ‘customers’
would normally comprise Production, Finance, Safety and Quality
departments). This may appear to be a somewhat pedantic proposal, but
experience indicates that it is a valuable precursor to establishing the
foundations for an effective maintenance system. The responsibilities and
objectives of all of the people involved in the management of the
maintenance function would be defined in such a policy document.
· Develop a
structure to drive continuous improvement in the Maintenance area, primarily
in the areas of availability and cost. This would require the establishment
of performance standards, measurements of performance, and a system for
initiating and executing improvement activity through root cause elimination
and the removal of avoidable work. Such a closed loop approach to
improvement lends itself to the introduction of objectives and targets for
improvement, and could be carried forward into processes for lifecycle
costing for selection and operation of new equipment.
· Carry out
FMECA on all production-critical and safety-critical equipment to generate
the optimum maintenance strategies, concentrating on CBM (Condition-Based
Maintenance) wherever appropriate. Experience across all industries
indicates that CBM is almost always a more effective basis for preventive
maintenance than fixed-interval maintenance in those situations where it is
technically appropriate. There are simple tools for carrying out effective
FMECA that would be applicable at Widget and it is recommended that they be
initially used on one critical piece of equipment for evaluation.
· Complete the
planned evaluation of a CMMS system. Based on the low cost of modern systems
it is likely that an entry-level system would prove to be justified in
Widget’s operational environment (PRIME can supply a simple evaluation
tool to assist with such an evaluation). The evaluation should extend beyond
the scheduling of PPMs to the broader need for relevant data to support the
improvement programme. Basic requirements for this would be the provision of
a formal work request system, the visibility of all maintenance work
(current and in history, ideally including materials and repair
times/costs), and facilities to associate and interrogate relevant failure
types/failure causes with breakdown events.
· Introduce a
formal downtime measurement and reporting system, including categories of
downtime events to improve the visibility of different types of equipment
failure. Set up a analysis system to support simple evaluation of downtime,
ideally with a cost base as well as time (PRIME can supply such a system
free of charge to client companies).
· Consider
further the value of an OEE-based programme for achieving overall production
loss reduction. Indications at Widget would suggest that the current level
of OEE is probably around 50%. In complex batch plant, a ‘Best Practice’
OEE level would be around 85%. The theoretical benefit to production
recoveries by improving OEE to around ‘Best Practice’ levels would,
therefore, be in the order of £2.1M per annum, with the maintenance
contribution probably in the order of £950k pa (the term ‘theoretical
benefit’ refers to the assumption that any additional output accruing from
OEE improvement could be converted into sales).
· Introduce a
system for condition-based inspection of all plant based on "3-Sense
Testing" involving both production operators and craftsmen, as the
starting point for a CBM approach to maintenance. It is very likely that the
FMECA approach suggested for determining the optimum PPM regime would result
in the present intrusive maintenance tasks being significantly replaced by
CBM tasks, including "3-Sense tests" wherever relevant.
· Evaluate the
use of acoustic emission measurement as the front-line tool for the
condition assessment rotating equipment, again as indicated in the FMECA
studies suggested. In Widget’s type of operation this is probably a more
effective tool than vibration analysis for assessing bearing failure, and is
non-intrusive to production. Simple methods and equipment are available that
could be used directly out by either operators or craftsmen.
· Develop
structured methods to involve production operators more fully in the
maintenance of their equipment. This will extend the principle of ownership
to the group that is best positioned to monitor and care for the health of
manufacturing equipment. Wide experience in industry has confirmed that the
extent of equipment maloperation and abuse is inversely proportional to the
extent of operator care, and it is usual for all low-level maintenance work
to be done by operators, freeing up maintenance craftsmen to do higher level
work. In the best companies, up to 30% of maintenance work might be carried
out by operators.
· Introduce a
system of budgeting and budget control for maintenance.
· Examine the
benefits to be gained from extending cross-skilling in the craftsmen team.
As the maintenance workforce have been with Widget for many years it is
likely that they will have some difficulties in becoming confident on some
of the recently acquired plant (eg the robotic assembly equipment), and
training in diagnostic techniques may also be appropriate for both
mechanical and electrical trades. In view of the entrenched Trade Union
culture, a basic ‘cost/benefit’ analysis should be carried out to decide
whether there is sufficient incentive to implement this aggressively, and if
so, to what extent any additional cross-skilling should be implemented. If
so, develop a strategy for implementing the changes indicated.
· Review the
level of compliance with L8 ACOP for Legionella.
· Introduce
lockoff/tagging systems for electrical isolation, and a programme of routine
testing of machine guards (recommended on a shift or daily basis).
· Review the
level of compliance with the Pressure Systems Regulations. {Top
of Page]
|